A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

What's the algebraic expression of "15 less than a number squared"?
If  lies in the quadrant IV. What can be the value of cos  ?
do u guys know the answer for 4/5b=16
what does alignment mean in dance?
is 7 over 9 , 5 over 12, and 5 over 8 terminating or repeating decimals? and what are they in decimals? please explain..thx :)
Can someone help me ?????
800 is 10 times as much as_____
what is m/9 - 1 = -2 whats the answer & steps
Write the number in two other forms: 0.632 --------- The example reads: 0.200 / 200 thousandths / 200 x 1/1000
Analyze how scientific thhought changes as new information is collected