if 12 people can finish a job by 5 days how many days will be required finish the same job by 10 people

Respuesta :

ishashunnny
ishashunnny ishashunnny
  • 01-09-2020

Answer:

4

Step-by-step explanation:

12p=5d

1p=5/12

10p=4.1666

≈4 days

Answer Link

Otras preguntas

When the fed purchases government securities from a commercial bank, the bank?
The weight of 10 identical samples of a substance is 0.1 pound. What is the weight of 10,000 samples?
Social learning theory can best be characterized as being concerned with:
Why did perrault particularly need the best sled dogs for his job?
What prompts reverend sykes to order that the doors be closed and that no one be allowed to leave for a period of time?
Hyperventilation during the preoxygenation phase of endotracheal intubation:
The following week the company was hired for a 225 mile move. If each truck traveled at hte same speed it has the previous week how long did the trip take for e
What is the "problem" with the way the u.s. census bureau defines "asian"?
The number of counties in state a and the number of counties in state b are consecutive even integers whose sum is 110110. if state a has more counties than sta
Created through the glass-steagall banking act of 1933, this originally protected up to $5,000 of an individual's bank account.: d created through the glass-ste