It takes 5 men 12 days ro complete a job how many days does it take 3 men to complete the job

Respuesta :

eloo59980
eloo59980 eloo59980
  • 04-01-2021

Answer:

5=12

3=? then Criss cross it and you will get 12*3 divided by 5 then you get 7.2

so the answer will be 7 days

Answer Link

Otras preguntas

If an advertisement puts an actor in a doctor's coat to try to persuade you to buy a product, which type of audience appeal is this, and why?
WILL GIVE BRAINLYST A flower pot is thrown out of a window with a horizontal velocity of 8 m/s. If the window is 1.5 m off the ground, how far from the window d
Which phrase correctly completes the following conversation? Pierre : Le bistro Chez Renée est le meilleur du coin. Franck : C’est vrai. Ils servent _________
Help please on these thanks
Which is the definition of the word borne as it is used in the excerpt below? A. a circular sofa B. to hold or remain firm under C. to support D. to give bir
According to freud, the hidden, unconscious desires expressed indirectly in a dream's symbolic content is its ________ content.
Which verb form best completes the following sentence? L’année dernière _______ les lundis, mercredis, et parfois les vendredis. A) je travailles B) je travai
When asked "what is the capital of south dakota?" participants who cannot initially remember the answer often show improved recall when given the prompt, "is it
The odds against an event are 7 to 1. find the probability that the event will occur.
help please Complete the equation of the line through (-9,7) and (-6,-3) y=mx+b format