it takes 8 labours 6days to complete a certain job.how many labours would complete the job in 15 days.​

Respuesta :

lakminirsenarath lakminirsenarath
  • 30-07-2021

Answer:

Step-by-step explanation:

Required man days to complete the job = 8 * 6

                                                                   = 48 Man Days

Required labors to complete the job by 15 days = 48/15

                                                                               = 3.2

It means, it is required 4 labors can complete the certain work by 15 days

Answer Link

Otras preguntas

Pls help me!! im giving brainliest
Donavan pitched 45 strikeouts in 36 innings. Bob pitched 96 strikeouts in 80 innings. Who had the best strikeout record?
Find the area of this sector and composite shape. Write your answer as an exact value and as a decimal, correct to two decimal places. Please someone answer
what are reasons why groups of people leave a paticular place
This Venn diagram represents the science subjects studied by students
The Star of David, pictured here represents which religion? Judaism Islam Hinduism Buddhism
Please help. 15 POINTS.
Need help ASAP Bob scored one third of the number of points that Bill scored. If Bob scored 24 points, how many points did Bill score?
Which table represents a function? A 2-column table with 4 rows. The first column is labeled x with entries negative 3, 0, negative 2, 8. The second column is l
Solve: 47 = -2 - 7x I need help