contestada

15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

One wall of Marsha’s greenhouse contains a window. What is the area of this wall of the greenhouse not including the area of the window?
Explain why you should use interjections only in casual communications
50 POINTS THIS IS A TIMED ASSIGNMENT PLEASE HELP Why did the Confederacy want to control Fort Sumter? a Fort Sumter was located in a Union state and controllin
Is psychological marketing ethical in your opinion?
Decide if the following sentence is grammatically correct or incorrect. Te conozco bien.
Does anyone know What does pH= ?
The daguerreotype process was inexpensive and easy for just about anyone to use
if the sales tax for the city of los angeles is 9.75 how much tax would you pap for an item that costs 200.00
The ice cream market is an example of _____ because it has many sellers who offer differentiated products.
In a uac prompt, what color is used to indicate the lowest level of risk?