In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Think of a real life situation that can be modeled by a proportion. Write a verbal model for the proportion and explain how it models the situation.
Discuss what variables are used to describe weather
What was the purpose of the Nuremberg Trials? to force Nazi leaders to answer for war crimes to decide if Truman had committed a crime by dropping atomic bombs
if C is an infinite set and B is a finite set then C\B is infinite set
What is a binomial nomenclature? a two word system for naming organisms by using the genus and species a two word system for naming organisms by using the famil
Choose the word that best fills-in the blank. _______ was rampant about whether or not the company was closing. A. Speculation B. Morose C. Proclamation
Which president's foreign policy achievements included peace agreements in Bosnia, Ireland, and the Middle East, as well as tariff treaties promoting internatio
Psychology involves the study of behavior in __________. A). Animals Only B). Humans Only C). Animals, Plants, And Humans D). Humans Only
Star Wars was the name given to which Reagan effort? Nuclear Arms Disarmament Nuclear Arms Race Strategic Defense Initiative Strategic Offense Initiative
Nutrients and oxygen diffuse into body cells from ______. A. Arteries B.the aorta C. Capillaries D.veins